What has been done

Continue to report on construction work on the Premier Resort Hotel site

  • the retaining wall anchoring process continues
  • preparatory work is carried out for the ventilation and chimney part of the boiler room
  • the slab of the 1st and 2nd step of the second section is flooded
  • the process of installing the columns of the first section continues.

What has been done

Dear Investors, we continue to inform you about the dynamics of the construction of the Premier Resort Hotel:

  • the work on the anchoring of the retaining wall is ongoing;
  • 100% complete roof overlay, staircase cell monolith of all balconies of the second sections
  • 90% of the aggregate masonry was completed in the second section,
  • the work on the bay piles is underway, preparation for concreting the first section of the first section is under way,
  • is preparing for bundles of reinforcement of the second ledge of the first section.

What has been done

Dear Investors, we continue to inform you about the dynamics of the construction of the Premier Resort Hotel:

  • completed monolithic works of section ІІ
  • the process of erection of internal walls from the gas block at the level of the 4th floor of the II section continues;
  • the work of ground works under the pits І section;
  • preparatory work is under way for the immersion of the first-stage booster piles.

What has been done

Dear Investors, we continue to inform you about the dynamics of the construction of the Premier Resort Hotel:

  • the work on filling the ceiling above the 5th floor has been completed;
  • the process of laying the outer walls 2-4
  • excavation works on the 1st pillar excavation started;
  • excavation works near the retaining wall for the walk zone;
  • concreting of the retaining wall of the first section;
  • the monolithic part of the second floor of the boiler is flooded;
  • the construction of the formwork under the bridge is under way

What has been done

Work on the construction site boils! There are 5 floors of the hotel (parking, commercial and 3 dwellings). The arrangement of the structures under the fill of slab floor 6 floor is underway. Call or visit our office for detailed project information! Details in sales departments.

What has been done

Dear Investors and potential buyers of apartments. Premier Resort Hotel! For your attention, another photo report from the hotel’s construction site. We value your confidence and implement our project dynamically! Work continues on the arrangement of the 5th floor of the hotel. Call or visit our office for project information!

What has been done

In February 2018, on the construction site were erected monolithic structures of the third floor and flooded floor slabs for the fourth. Reinforced concrete structures are warmed up with the help of powerful electronic heaters. From the side of the road there is a load-bearing wall with a height of 7.5 meters. In parallel, excavation works on a sample of soil for the installation of the boiler house and part of the parking. Filling the boiler room walls is complete. The completion of construction is scheduled for 2019. The work goes ahead of the schedule, despite the weather and climatic conditions. The next stage is the construction of monolithic structures of the fourth floor.

What has been done

At the construction site Premier Resort Hotel completed work on filling the ceiling of the third floor and started – with the installation of the frame of the 4th floor!

We remind you that the number of rooms is rapidly decreasing, book an overview of the building or book apartments on the phone + 38- 068-394-00-44.

Stay up informed – be the first to learn about the “Premier Resort” news!

* No spam, notifications only

Get progress reports on the construction

Thank you, you will receive progress reports on the construction

Lasă o cerere și te sunăm

Mulțumim!

Mesajul Dumneavaostră a fost expediat!