What has been done

Construction work on the site of the Premier Resort Hotel:

  • drilling works on the first section on the 5th aggression continue
  • installation of piles and drainage tray in the first section
  • partially mounted vertically in the first section
  • 3 sections of the foundation plate are poured

What has been done

Continue to report on construction work on the Premier Resort Hotel site:

  • 100% completed work to strengthen the retaining wall,
  • concreting slab 3 sections,
  • completed concreting of technical premises of the 1st section of the 2nd scarp,
  • 100% complete the knitting of piles in section 1.

What has been done

Continue to report on construction work on the Premier Resort Hotel site

  • the retaining wall anchoring process continues
  • preparatory work is carried out for the ventilation and chimney part of the boiler room
  • the slab of the 1st and 2nd step of the second section is flooded
  • the process of installing the columns of the first section continues.

What has been done

Dear Investors, we continue to inform you about the dynamics of the construction of the Premier Resort Hotel:

  • the work on the anchoring of the retaining wall is ongoing;
  • 100% complete roof overlay, staircase cell monolith of all balconies of the second sections
  • 90% of the aggregate masonry was completed in the second section,
  • the work on the bay piles is underway, preparation for concreting the first section of the first section is under way,
  • is preparing for bundles of reinforcement of the second ledge of the first section.

What has been done

Dear Investors, we continue to inform you about the dynamics of the construction of the Premier Resort Hotel:

  • completed monolithic works of section ІІ
  • the process of erection of internal walls from the gas block at the level of the 4th floor of the II section continues;
  • the work of ground works under the pits І section;
  • preparatory work is under way for the immersion of the first-stage booster piles.

What has been done

Dear Investors, we continue to inform you about the dynamics of the construction of the Premier Resort Hotel:

  • the work on filling the ceiling above the 5th floor has been completed;
  • the process of laying the outer walls 2-4
  • excavation works on the 1st pillar excavation started;
  • excavation works near the retaining wall for the walk zone;
  • concreting of the retaining wall of the first section;
  • the monolithic part of the second floor of the boiler is flooded;
  • the construction of the formwork under the bridge is under way

Stay up informed – be the first to learn about the “Premier Resort” news!

* No spam, notifications only

Get progress reports on the construction

Thank you, you will receive progress reports on the construction

Lasă o cerere și te sunăm

Mulțumim!

Mesajul Dumneavaostră a fost expediat!