What has been done

Your photo report:

  • 99% finished floor-to-wall monolithic work
  • Roofing work is ongoing
  • staircase installation
  • 100% complete preparation for the installation of the chimney system

What has been done

Despite the difficult weather conditions, construction work at the Premier Resort Hotel is actively underway

Another photo report from the construction site of the Premier Resort Hotel

  • The second floor of the first section of the hotel was built
  • Monolithic works are underway to block the first living floor of the first section of the hotel;
  • 100% complete installation of panoramic windows in the second section.

What has been done

Another photo report from the construction site of the Premier Resort Hotel

  • continues monolithic work at the level of the first residential floor of the first section of the hotel.
  • 100% availability of the second section of the staircase
  • 100% completed work in the technical rooms of the second section

What has been done

Difficult weather conditions did not affect the pace of construction of Premier Resort Hotel.

The process of concreting the floors of the first section of the hotel is actively going on now.

We introduce you to the photo report

  • 100% completed raising the vertical to zero on the first section
  • reinforcement is mated, formwork is placed and concrete is placed on the 1st floor of the first section
  • completed work on the development of soil drainage

What has been done

Construction work on the site of the Premier Resort Hotel:

  • drilling works on the first section on the 5th aggression continue
  • installation of piles and drainage tray in the first section
  • partially mounted vertically in the first section
  • 3 sections of the foundation plate are poured

What has been done

Continue to report on construction work on the Premier Resort Hotel site:

  • 100% completed work to strengthen the retaining wall,
  • concreting slab 3 sections,
  • completed concreting of technical premises of the 1st section of the 2nd scarp,
  • 100% complete the knitting of piles in section 1.

What has been done

Continue to report on construction work on the Premier Resort Hotel site

  • the retaining wall anchoring process continues
  • preparatory work is carried out for the ventilation and chimney part of the boiler room
  • the slab of the 1st and 2nd step of the second section is flooded
  • the process of installing the columns of the first section continues.

Stay up informed – be the first to learn about the “Premier Resort” news!

* No spam, notifications only

Get progress reports on the construction

Thank you, you will receive progress reports on the construction

Lasă o cerere și te sunăm

Mulțumim!

Mesajul Dumneavaostră a fost expediat!